Running Status of VANDE BHARAT .. (22457)

Origin Start Date 27-04-2025
Train has reached destination DEHRADOON (DDN) at 22:34 27-Apr-2025.
NoStation NameSch. ArrivalSch. DepartureActual Arrival (Delay)
Actual Departure (Delay)
Actual Departure (Delay)DistanceKm's
1ANAND VIHAR TRMSource17:50Source
17:52, 27 Apr (-2m)
17:52, 27 Apr (-2m)-302
2MEERUT CITY18:3618:3818:52, 27 Apr (-16m)
18:53, 27 Apr (-15m)
18:53, 27 Apr (-15m)-242
3MUZAFFARNAGAR19:0819:1019:28, 27 Apr (-20m)
19:30, 27 Apr (-20m)
19:30, 27 Apr (-20m)-186
4DEOBAND19:2619:2819:46, 27 Apr (-20m)
19:48, 27 Apr (-20m)
19:48, 27 Apr (-20m)-162
5SAHARANPUR20:0020:0520:12, 27 Apr (-12m)
20:18, 27 Apr (-13m)
20:18, 27 Apr (-13m)-128
6ROORKEE20:3120:3320:42, 27 Apr (-11m)
20:45, 27 Apr (-12m)
20:45, 27 Apr (-12m)-93
7HARIDWAR JN21:1121:1521:21, 27 Apr (-10m)
21:23, 27 Apr (-8m)
21:23, 27 Apr (-8m)-52
8DEHRADUN22:35Destination22:34, 27 Apr (+1m)
Destination
Destination
 Updated at: 22:43, 27th April 2025 IST