Running Status of GOMTESHWARA EXP (16576)

Origin Start Date 01-05-2026
Train has reached destination YESVANTPUR JN. (YPR) at 15:59 01-May-2026.
NoStation NameSch. ArrivalSch. DepartureActual Arrival (Delay)
Actual Departure (Delay)
Actual Departure (Delay)DistanceKm's
1MANGALORE JNSource07:00Source
07:00, 01 May (RT)
07:00, 01 May (RT)-413
2BANTAWALA07:3307:3507:25, 01 May (+8m)
07:35, 01 May (RT)
07:35, 01 May (RT)-393
3KABAKAPUTTUR08:2008:2208:41, 01 May (-21m)
08:46, 01 May (-24m)
08:46, 01 May (-24m)-369
4SUBRAHMANYA ROA09:0009:1009:31, 01 May (-31m)
09:44, 01 May (-34m)
09:44, 01 May (-34m)-327
5SAKLESHPUR11:3011:4012:06, 01 May (-36m)
12:14, 01 May (-34m)
12:14, 01 May (-34m)-216
6HASSAN12:4512:5513:00, 01 May (-15m)
13:02, 01 May (-7m)
13:02, 01 May (-7m)-174
7CHANNARAYAPATNA13:2313:2413:32, 01 May (-9m)
13:33, 01 May (-9m)
13:33, 01 May (-9m)-141
8SHRAVANBELAGOLA13:3413:3513:45, 01 May (-11m)
13:46, 01 May (-11m)
13:46, 01 May (-11m)-133
9B.G. NAGAR14:0514:0614:13, 01 May (-8m)
14:16, 01 May (-10m)
14:16, 01 May (-10m)-99
10YEDIYURU14:1914:2014:29, 01 May (-10m)
14:30, 01 May (-10m)
14:30, 01 May (-10m)-84
11KUNIGAL14:3514:3614:43, 01 May (-8m)
14:44, 01 May (-8m)
14:44, 01 May (-8m)-67
12NELAMANGALA15:1415:1515:28, 01 May (-14m)
15:30, 01 May (-15m)
15:30, 01 May (-15m)-22
13CHIK BANAVAR15:4415:4515:45, 01 May (-1m)
15:48, 01 May (-3m)
15:48, 01 May (-3m)-8
14YESVANTPUR JN16:30Destination15:59, 01 May (+31m)
Destination
Destination
 Updated at: 20:58, 1st May 2026 IST